Allocation rate per packing order by activity-based costing


Question 1: Committed resources

a) are supplied as needed.
b) are acquired by a contract for the exact amount of their usage.
c) may exceed the demand for their usage.
d) All of the above are correct.

Question 2: During September, 40,000 units were produced. The standard quantity of material allowed per unit was 5 pounds at a standard cost of $2.50 per pound. If there was a favorable usage variance of $25,000 for September, the actual quantity of materials used must have been

a) 210,000 pounds.
b) 190,000 pounds.
c) 105,000 pounds.
d) 95,000 pounds.

Question 3: Zipp Company manufactures two products (X and Y). The overhead costs ($84,000) have been divided into three cost pools that use the following activity drivers:

Product   Number of Setups    Machine Hours     Packing Orders
X                     10                         500                      75
Y                     10                       2,000                    175
 
Cost per pool $9,000                  $60,000               $15,000
 
What is the allocation rate per packing order using activity-based costing?

 a) $15,000
 b) $60
 c) $7,500
 d) $200

Question 4: If a support department's costs were budgeted to be $150,000 and actual costs incurred by the support department were $200,000, the total amount of the support department's costs that should be allocated to other departments is

 a) $350,000.
 b) $200,000.
 c) $150,000.
 d) $50,000.

Question 5: _______________ is (are) a cost accounting system that uses only unit-based activity drivers to assign costs to cost objects.

 a) Activity-based management
 b) Activity-based costing system
 c) Functional-based cost management system
 d) Both a and b

Question 6: Spoilage in a process costing process means

 a) fewer units leave the process than enter it.
 b) fewer units enter a process than leave it.
 c) a process is no longer viable.
 d) products are receiving too much attention.

Question 7: The predetermined overhead rate is usually calculated

 a) at the end of each month.
 b) at the beginning of each month.
 c) at the beginning of the year.
 d) at the end of the year.

Question 8: For a labor-intensive manufacturing operation, which of the following would be the most appropriate activity driver?

 a) machine hours
 b) direct labor hours
 c) number of employees
 d) units of output

Question 9: _______________ refers to the assignment of indirect costs to cost objects.

 a) Allocation
 b) Direct tracing
 c) Physical observation
 d) Cost management

Question 10: The following information is provided:

Estimated manufacturing overhead    $690,000
Estimated machine hours                     46,000
Actual machine hours worked               50,000
 
Actual costs incurred:

Indirect materials              $170,00
Indirect labor                    230,000
Utilities                             120,000
Insurance                         100,000
Rent                                  80,000
 

The amount of overapplied or underapplied overhead is

 a) $65,200 underapplied.
 b) $60,000 overapplied.
 c) $50,000 overapplied.
 d) $10,000 underapplied.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Allocation rate per packing order by activity-based costing
Reference No:- TGS01905998

Now Priced at $20 (50% Discount)

Recommended (96%)

Rated (4.8/5)