Question:

Kumar Company has two Producing Departments and two Support Centers. The following budgeted data pertain to these four departments:

 

Support Departments

Producing Departments

 

Maintenance

Personnel

Assembly

Painting

Overhead

$2,00,000

$60,000

$43,000

$74,000

Square Footage

-

2,700

5,400

5,400

No. of employees

30

-

72

198

Direct labour hours

-

-

25,000

40,000

Required:

1. Allocate the Overhead Costs of the Support Departments to the Producing Departments using the Direct Method. Explain with reasoning the basis on which allocation has been done.

2. Using Direct labour Hours compute departmental Overhead rates for the two Producing Departments.

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Allocate the overhead costs of the support departments