All resource leveling techniques involve resource leveling


1. All resource leveling techniques involve

A.Delaying noncritical activities

B. Delaying critical activities

C. Using negative slack

D. Both A and C are correct

E. A, B, and C are all correct

2. Resource leveling can provide

A. Lower peak demand

B. Reduced resource need over the life of the project

C. Reduced fluctuations in resource demand

D. Both A and B are correct

E. A, B, and C are all correct

3. In a resource-constrained project, the first priority in assign activities with the

A. Smallest duration

B. Least slack

C. Most slack

D. Lowest identification number

E. Highest cost

4. A project budget report is showing our project as spending $40,000. Which of the following is true?

A. We are spending less than we should for the project

B. We are doing a good job managing the project

C. We should check to see if all the bills have been paid

D. Both A and B are correct

E. We can't be sure how the project is going

Request for Solution File

Ask an Expert for Answer!!
Project Management: All resource leveling techniques involve resource leveling
Reference No:- TGS02296448

Expected delivery within 24 Hours