All labour and materials costs are variable skilled labour


Question: Darmor Ltd has three products, which require the same production facilities. Information about the production costs for one unit of its products is as follows:

Product                                    X                 Y                 Z

                                               £                 £                 £

Labour: Skilled                          6                 9                 3

            Unskilled                       2                 4                10

Materials                                  12                25               14

Other Variable costs                  3                  7                 7

Fixed costs                               5                 10                10

All labour and materials costs are variable. Skilled labour is paid £12 an hour, and unskilled labour is paid £10 an hour. All references to labour costs above, are based on basic rates of pay. Skilled labour is scarce, which means that the business could sell more than the maximum that it is able to make of any of the three products. Product X is sold in a regulated market, and the regulators have set a price of £30 per unit for it.

Required:

(a) State, with supporting workings, the price that must be charged for products Y and Z, such that the business would find it equally profitable to make and sell any of the three products.

(b) State, with supporting workings, the maximum rate of overtime premium that the business would logically be prepared to pay its skilled workers to work beyond the basic time.

 

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: All labour and materials costs are variable skilled labour
Reference No:- TGS02233422

Expected delivery within 24 Hours