After several investigations of points outside control


Type I error (alpha risk). After several investigations of points outside control limits revealed nothing, a manager began to wonder about the probability of a type I error for the control limits used (z= 1.90). a) Determine the apha risk (i.e.< P [Type I error]) for this value of z. b) What z would provide an alpha risk of about 2 percent?