After evaluating a capital budgeting project susan


After evaluating a capital budgeting project, Susan discovered that the project’s NPV > 0. What does this information tell us about the project’s IRR and discounted payback (DPB)? Can anything be concluded about the project’s traditional payback period (PB)?