After all of the houses are built and before all are sold


In a housing project the following sequence of events occurs.

  • At the start of the project (time zero), land is bought at $1,000,000
  • Two months later, $100,000 is paid to the architect for preparing the design
  • In month 4, construction is started and the cost of construction (labor and material) is $150,000per month
  • Every month, one house is built (a total of 12 houses); the first one is ready for sale in month 6
  • During every month starting from month 8, one house is sold for a price of $150,000 each
  • After all of the houses are built and before all are sold, the cost of maintaining the site is $10,000per monthDraw the cash flow diagram.