Adam munson was able to determine that expected project


Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 9.

a) The probability that the project will be completed in 15 months = (round your response to four decimal places).

b) The probability that the project will be completed in 23 months =  (round your response to four decimal places).

c) The probability that the project will be completed in 27 months =  (round your response to four decimal places).

d) The probability that the project will be completed in 33 months =  (round your response to four decimal places).

e) The due date that yields a 95% chance of completion = __________ months (round your response to two decimal places).