Accept the panda project


Problem:

Calculate the following two projects' payback period

Year Panda Project Peacock Project
0 -450 -450
1 350 100
2 100 350
3 30,000 3

Required:

Question 1: Assume we will accept the project with PP<= 3years.

Question 2: According to the PP rule, should we accept the Panda project? should we accept the peacock project?

Question 3: According to the NPV rule, should we accept the Panda project? should we accept the peacock project? (assume a 12% required rate of return)

Note: Please explain comprehensively and give step by step solution.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Accept the panda project
Reference No:- TGS0884318

Expected delivery within 24 Hours