Abagail corp uses activity-based costing system with three


Problem - Abagail Corp. uses activity-based costing system with three activity cost pools. The following information is provided:

Costs: Wages and salaries

$200,000

Depreciation

114,000

Utilities

111,000

Total

$440,000

Activity Cost Pools

 

Assembly

Setting Up

Other

Wages and salaries

0.58

30%

10%

Depreciation

0.36

45%

20%

Utilities

0.21

40%

30%

Required - How much total cost would be  allocated to the Assembly activity cost pool?