A what is the energy rate btumin for heating the


Industrial buildings have fresh air requirements depending on the occupancy level and its function. Assume 15,000 cfm of moist air from the outdoors, which is at 32°F and a relative humidity of 80%, is heated to 70°F in order to provide a supply of fresh air to the inside of an office building.

a. What is the energy rate (Btu/min) for heating the air?

a. What is the relative humidity of the air after heating? If water vapor was added to the 70°F air to increase its relative humidity to 50%, what is the mass flow rate (Ibm/min) of water vapor required?

b. What is the daily cost of heating this building by using natural gas if the gas cost is $0.5 per therm where a therm is 100,000 Btu's?

Solution Preview :

Prepared by a verified Expert
Chemistry: A what is the energy rate btumin for heating the
Reference No:- TGS02741400

Now Priced at $15 (50% Discount)

Recommended (98%)