A two-step process is used to finish a product painting and


A two-step process is used to finish a product: painting and drying. There are 5 workers and each one takes an average of 60 minutes to paint each unit. Drying takes place in an oven that can hold up to 100 units and it takes 5 minutes to load each unit. Once all the units are loaded into the oven, it takes 6 hours to dry each load. What fraction of time is the oven being loaded if C&A uses a batch size of 100 and demand is unlimited?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A two-step process is used to finish a product painting and
Reference No:- TGS02451463

Expected delivery within 24 Hours