A time study analyst observed a job that is performed


A recently negotiated union contract allows workers in a shipping department 24 minutes for rest, 10 minutes for personal time, and 14 minutes for delays for each four hours worked. A time study analyst observed a job that is performed continuously and found an average time of 6.0 minutes per cycle for a worker she rated at 95 percent. What standard time is applicable for that operation?

Solution Preview :

Prepared by a verified Expert
Operation Management: A time study analyst observed a job that is performed
Reference No:- TGS01218861