A supervisor needs to produce metal nameplates for bicycles. Two machines are available. The first requires a single die that costs $600. The plates will take 3 minutes each to produce at a total cost of $60 an hour. The second machine requires no initial expense but takes 6 minutes to produce at a total cost of $60 an hour. Calculate the break-even point.