A study undertaken by the materials management department


A firm wishes to determine the efficiency and utilization of a work center composed of 3 machines each working 16 hours per day for 5 days a week. A study undertaken by the materials management department found that over the past year the work center was available for work 12,000 hours, work was actually being done for 10,000 hours, and work was performed 11,480 standard hours. Calculate the utilization, efficiency, and demonstrated weekly capacity. Assume a 50-week year.

Request for Solution File

Ask an Expert for Answer!!
Mechanical Engineering: A study undertaken by the materials management department
Reference No:- TGS01629491