A software development project at day 70 exhibits an actual


A software development project at day 70 exhibits an actual cost of 78,000.00 and a scheduled cost of $84,000.00. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate time variance.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A software development project at day 70 exhibits an actual