A small software development project has five major activities. The times are estimated and provided in the table below (measured in days)

Acitivity Predecessor a m b

A -- 2 5 8

B -- 10 10 10

C A 4 7 10

D B 2 5 14

E C 3 3 3

(a) What is the expected completion time for this project?

(b) What are the critical activites?

(c) What is he probability that the project could be completed in 17 day?