A small software development project at krishna dhirs firm


A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below:

Activity --------Immediate Predecessor -------a---------m-------b

A----------------- --------- ----2------- 5 -----8

B----------------- --------- ----3------- 6 -----9

C----------------- A -----4----- 7 -----10

D----------------- B ----2------- 5 -----14

E----------------- C ----3------- 3 -----3

The expected completion time for this project is ______(Whole Number)

The project variance value of completion time is ____ ( Whole Number)