A six-stage process goes through the sequence of machines


A six-stage process goes through the sequence of machines 1-2-3-4-5-6. Each machine dis. cards 7 percent scrap. The current demand is 2000 good units per day. (a) Determine the number of units per day started in the third stage (machine 3). (b) The standard time per part processed at the third stage is 2.5 minutes. The corresponding machine requires a 15. minute setup every day. Assuming one daily 8-hour shift, and a machine availability factor equal to 0.85, find the fractional number of machines required in the third-stage operation.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A six-stage process goes through the sequence of machines
Reference No:- TGS02573041

Expected delivery within 24 Hours