A sewer pipe must be laid from a starting invert elevation


A sewer pipe must be laid from a starting invert elevation of 650.73 ft at station 9 + 25 to an ending invert elevation of 653.81 ft at station 12 + 75. Determine the uniform grade needed, and calculate invert elevations at each 50-ft station.