A schedule calls for producing 40 as 20 bs and 30cs process


A schedule calls for producing 40 As, 20 Bs, and 30Cs. Process time is 5 minutes per A, 8 minutes per B, and 10 minutes per C.

a) Develop the mixed model repeating sequence. Assuming 60 seconds changeover between products, how long will the scheduled production take?

b) Assume no more than 700 minutes a day is available to produce these products. Suggest a way to reduce the required production time to meet this constraint.