A project under consideration has a net present value of


A project under consideration has a net present value of $10,000 for a required investment of $60,000. There are no other investment options at this time. However, the assumed discount rate used to calculate the net present value is 20%.

On the basis of this information alone, this project should:

Definitely be rejected because $10,000 is only 17% of $60,000

Be rejected on the basis that the project loses $50,000

Probably be approved since the net present value is greater than zero

Be accepted if the cost of capital is greater than or equal to 20 percent

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: A project under consideration has a net present value of
Reference No:- TGS01072646

Expected delivery within 24 Hours