A project has the following estimated data price 100 per


A project has the following estimated data: price = $100 per unit; variable costs = $51 per unit; fixed costs = $6,200; required return = 8 percent; initial investment = $7,000; life = five years. Ignore the effect of taxes. What is the accounting break-even quantity?What is the cash break-even quantity?What is the financial break-even quantity? What is the degree of operating leverage at the financial break-even level?