A project has suffered a cost and schedule setback what is


A project has suffered a cost and schedule setback. The variances identified in the project have been found to be atypical. Given that the BAC is $6000.00, the Earned value is $4,500.00 and the CPI 1.5, what is the Estimate at Completion (EAC).