A project has just completed its 87th item in the project


A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nearly $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?