A project has just completed its 87th item in the project


A project has just completed its 87th item in the project plan. It was scheduled to have spent $147,000 at this point in the plan, but has actually spent only $135,000. The project manager estimates that the value of the work actually finished is nearly $127,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A project has just completed its 87th item in the project
Reference No:- TGS01102545

Expected delivery within 24 Hours