A project has an initial cost of 160000 and an estimated


A project has an initial cost of $160,000 and an estimated salvage value after 14 years of $100,000. Estimated average annual revenues are $28,000. Estimated average annual costs are $16,000. Assuming that annual revenues and costs will be uniform, compute the rate of return for this investment.