A project being analyzed by pert has 55 activities 8 of


A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project a 23% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A project being analyzed by pert has 55 activities 8 of
Reference No:- TGS02599125

Expected delivery within 24 Hours