A production process at kenneth day manufacturing is shown


Question -

A production process at Kenneth Day Manufacturing is shown in Figure. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A prod

1851_Figure.png

a) Which operation is the bottleneck?

b) What is the bottleneck time?

c) What is the throughput time of the overall system?

d) If the firm operates 8 hours per day, 20 days per month, what is the monthly capacity of the manufacturing process?