A production process at kenneth day manufacturing is shown


A production process at Kenneth Day Manufacturing is shown in Figure. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).

a) Which operation is the bottleneck?

b) What is the bottleneck time?

c) What is the throughput time of the overall system?

d) If the firm operates 8 hours per day, 20 days per month, what is the monthly capacity of the manufacturing process?

2349_Figure.png

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A production process at kenneth day manufacturing is shown
Reference No:- TGS02156647

Expected delivery within 24 Hours