A production line at vj sugumarans machine shop has three


A production line at vj sugumaran's machine shop has three stations. The first station can process a unit in 10 minutes. The second has two identical machines, each of which can process a unit in 12 minutes( each unit only needs to be processed one of two machines). The third station can process a unit in 8 minutes. Which station is the bottleneck station?