A plant has three work centers that are capacity


A plant has three work centers that are capacity constraints. Two products are produced, each using the critical work centers. Which of the following techniques would be used to systematically construct a Master Production Schedule that will optimize profit for the company?

A) Rough-Cut Capacity Planning

B) Capacity Requirements Planning

C) Line Balancing

D) Linear Programming