A petroleum company recently completed construction on a


A Petroleum company recently completed construction on a large refinery in Louisiana. The final construction cost was $71,000,000. The refinery covers a total of 260 acres. The Expansion and Acquisition Department at the company is currently working on plans for a new refinery in Texas. The anticipated size is approximately 360 acres. If the power-sizing exponent for this type of facility is .70, what is the estimated cost of construction?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: A petroleum company recently completed construction on a
Reference No:- TGS02390478