A node has one entering activity a and two leaving


A node has one entering activity, a, and two leaving activities, b and c. Given the following information, determine the latest starting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc = 27; activity times are a = 4, b = 6, c = 8.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A node has one entering activity a and two leaving
Reference No:- TGS01678189

Expected delivery within 24 Hours