A new order of 600 units must be completed in 4 days how


A company has several machines that can be used to manufacture a product.Each unit of product requires 21 minutes of manufacturing time. Amachine can be used 6.4 hours per day and 22 days per month. A new order of 600 units must be completed in 4 days how many machines must be used to fullfil the order?

1. One machine can manufacture how many units

2. The company must use how many machines

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A new order of 600 units must be completed in 4 days how
Reference No:- TGS02456867

Expected delivery within 24 Hours