A new 21-kw power substation was built in county a for 14


A new 21-kW power substation was built in County A for 1.4 million dollars. County B, a neighboring county, is planning on building a similar though smaller substation. An 18-kW substation is planned for County B. If the power sizing exponent is .80 for this type of facility what is the estimated cost of construction?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A new 21-kw power substation was built in county a for 14
Reference No:- TGS01528436