Question: A new 2-lane road is needed in a part of town that is growing. At some point the road will need 4-lanes to handle the anticipated traffic. If the city's optimistic estimate of growth is used, the expansion will be needed in 4 years. For the most likely and pessimistic estimates, the expansion will be neededin 8 and 15 years, respectively. The expansion will cost $4.2 million. Use an interest rate of 8%.

(a) What is the PW for each scenario, and what is the range of values?

(b ) Use Equation 10-1 to find the mean value of the expansion's PW Probabilities.