A network based schedule has four paths namely 789 and 10


A network based schedule has four paths, namely, 7,8,9 and 10 weeks. If the 10 week path is compressed to 8 weeks, then Select one: a. The 9 week path is now the critical path b. We now have two critical paths c. Not enough information is provided to make a determination d. Only the 7-week path has slack