A method for estimating the impacts of uncertainty on


1. When developing risk mitigation plans, one should:

a) Be sure to plan for every possible thing that could go wrong.

b) Have a single person develop all risk scenarios .

c) Always use buffers as the primary risk mitigation technique.

d) Select mitigation plans that give the highest level of prevention or protection at the lowest investment.

2. A method for estimating the impacts of uncertainty on project tasks is:

a) Rule of thumb estimates.

b) Best case estimates.

c) Probabilistic task duration estimates.

d) Risk weighted estimates.

3. Which of the following is NOT a good reason to terminate (kill) a project?

a) Consistent budget and schedule overruns.

b) Changing organizational priorities.

c) Uncertainty regarding the project’s outcomes.

d) Wrong resources assigned to the project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A method for estimating the impacts of uncertainty on
Reference No:- TGS02939300

Expected delivery within 24 Hours