A manufacturing process consists of three sequential operations. At maximum capacity operation A can output 125 units per hour, Operation B can output 120 units per hour, and Operation C can output 130 units per hour. There is one worker assigned to each of the three operations. Working at the maximum capacity level, what would be the output of this process in an 8 hour work day?