A manufacturer has an assembly line with 3 processes


A manufacturer has an assembly line with 3 processes operating one shift per day. A feeds B and B feeds C. Process A can produce 300 parts per hour. Process B can produce 200 parts per hour and C produces 120 parts per hour. Mr.? Nimwit, the? boss, has a great? idea: add an extra shift for all 3 processes. The result will? be:

A. Total production is 1240 finished goods per day.

B. Mr. Nimwit actually ends up paying one person on each shift to do nothing for over 4 hours per day

C. Production goes up to 400 finished goods per day

D. Production goes up top 600 finished goods per day