A manufacturer can produce 12000 bearings per day the


A manufacturer can produce 12000 bearings per day. The manufacturer received an order of 8000 bearings per day from a customer. The cost of holding a bearing in stock is Rs.0.20 per month. Setup cost per production run is Rs.500. Assuming 300 working days in a year, the frequency of production run should be

(A) 4.5 days

(B) 4.5 months

(C) 6.8 days

(D) 6.8 months