A manager must decide between two machines what are the


A manager must decide between two machines. The manager will take into account each machine’s operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 137 hours and a projected average repair time of 4 hours. Projected times for machine B are an average operating time of 67 hours and a repair time of 3 hours. What are the projected availabilities of each machine? (Round your answers to 3 decimal places.)

Availability:

Machine A

Machine B

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A manager must decide between two machines what are the
Reference No:- TGS02884143

Expected delivery within 24 Hours