A manager must decide between two machines the manager will


A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair times.

Machine A has a projected average operating time of 140 hours and a projected average repair time of 10 hours. Projected times for machine B are an average operating time of 55 hours and a repair time of 3 hours.

What are the projected availabilities of each machine? (Round your answers to 3 decimal places.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A manager must decide between two machines the manager will
Reference No:- TGS02652500

Expected delivery within 24 Hours