A manager intends to order a new machine and must now


A manager intends to order a new machine and must now decide on the number of spare parts to order along with the machine. The parts cost $400 each and have no salvage value. The manager has compiled a frequency distribution for the probable usage of spare parts, as shown. For what range of shortage costs would stocking one spare part constitute an optimal decision?

No. of

Spares Frequency

0 .08

1 .30

2 .24

3 .20

4 .18