A machine shop located on the outskirts of los angeles


Question: A machine shop located on the outskirts of Los Angeles accepts custom orders from a number of high-tech firms in southern California. The machine shop consists of four departments: A (lathes), B (drills), C (grinders), and D (sanders). The from-to chart showing distances in feet between department centers is given here.

66_Dep 1.png

The shop has accepted orders for production of four products: P1, P2, P3, and P4. The routing for production of these products and the weekly production rates are

829_Rout.png

Assume that products are produced in batches of size 25.

a. Convert this information into a from-to chart giving numbers of materials handling trips per week between departments.

b. If the cost to transport one batch 1 foot is estimated to be $1.50, convert the from to chart you found in part (a) to one giving the materials handling cost per week between departments.

c. Develop an activity relationship chart for these four departments based on the results of part (b). Assume that A is assigned to the highest cost and O to the least, with the rankings E and I assigned to the costs falling in between the extremes.

d. Suppose that the machine shop is located in a building that is 60 feet by 80 feet. Furthermore, suppose that departments are rectangularly shaped with the

1317_11-32.png

1176_Dim.png

Sketch a layout consistent with the rel chart you obtained in part (c).

Request for Solution File

Ask an Expert for Answer!!
Database Management System: A machine shop located on the outskirts of los angeles
Reference No:- TGS02265246

Expected delivery within 24 Hours