A law firm handles two types of insurance policies policy 1


A law firm handles two types of insurance policies. Policy 1 requires 4 hours of Resource 1. 1 hours of Resource 2. and 1 hours of Resource 3. Policy 2 requires 5 hours of Resource 1. 3 hours of Resource 2 and 1 hours or Resource 3. There are 5 units or Resource 1, 3 units or Resource 2, and 3 units of Resource 3. Working hours per day is 8 hours Capacity waste factor tor resources 1 to 3 is 0.1. 0.3 and 0.2 respectively. Product mix includes 0.2 product 1 and the rest is product 2.

1. What is the effective daily capacity of the process?

2. Compute the cycle time.

3. Suppose utilization of the process is 0.8. Compute the daily throughput.

4. On average how many flow units are with the resources (in the processors)