A job was timed for 60 cycles and had an average of 14


A job was timed for 60 cycles and had an average of 1.4 minutes per piece. The performance rating was 90 percent, and workday allowances are 14 percent. Determine each of the following:

a. Observed time. (Round your answer to 1 decimal place.)

  Observed time minutes

b. Normal time. (Round your answer to 2 decimal places.)

  Normal time minutes

c. Standard time. (Round your answer to 2 decimal places.)

  Standard time minutes

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A job was timed for 60 cycles and had an average of 14
Reference No:- TGS02214943

Expected delivery within 24 Hours