A jit system uses kanban cards to authorize movement of


A JIT system uses Kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 84 parts per hour while running. The manager has assigned an inefficiency factor of 0.24 to the center.

Standard containers are designed to hold 5 dozen parts each. The cycle time for parts containers is 105 minutes.

How many containers are needed?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A jit system uses kanban cards to authorize movement of
Reference No:- TGS02599013

Expected delivery within 24 Hours