A guidance and detection system is being built as part of a


Question: A guidance and detection system is being built as part of a large defense project. The detection portion consists of radar and sonar subsystems. Separate equipment is required for each of the subsystems. In each case, the equipment must be calibrated prior to production. After production, each subsystem is tested independently. The radar and the sonar are combined to form the detection system, which also must be tested prior to integration with the guidance system. The final test of the entire system requires complex equipment. The activities and the activity times are

494_Activity 3.png

a. Construct a network for this project.

b. Determine the earliest and the latest starting and finishing times for all the activities, and identify the critical path.

c. Draw a Gantt chart for this project based on the earliest times.

d. How much time is available for assembling and calibrating the final test gear without delaying the project?

e. What are the activities that must be completed by the end of 10 days to guarantee that the project is not delayed?

f. What are the activities that must be started by the end of 10 days to guarantee that the project is not delayed?

g. Solve this problem using linear programming.

Request for Solution File

Ask an Expert for Answer!!
Data Structure & Algorithms: A guidance and detection system is being built as part of a
Reference No:- TGS02265138

Expected delivery within 24 Hours